Mornington Railway
The long serving Secretary of the railway, Howard
Girdler, has retired after 25 years service with the
line.
Steam locomotive K163 will be out of service for
most of the year undergoing heavy maintenance This leaves the
line without an operational steam engine. The engine
requires a new boiler to replace its existing one
and fortunately they are able to use the one belonging to K191.
This boiler
had first to be rebuilt to allow it to replace
K 163's boiler and as part of the work a temporary
roof was constructed over it and a machine shop has
had to be set up. As part of the work a new ash pan
has had to be made. K191's boiler has had some
boiler stays and tubes replaced and badly rusted
plate around the smoke box cut away and replaced. The
boiler has been pressure tested and approved by the
boiler inspector. It is expected the boiler will be
placed in K 163's frame in August.
Services are being run using both diesel engines T332
and T411
The New Year's Eve train proved successful and an
orientation day was recently held with 17 people
present. As is usual track maintenance is
continuing with work in the cutting near Horse
Crossing. The next section to receive attention will
be in Moorooduc itself.
The railway has installed a 11,200 litre water tank
specifically for the CFA to use to fight
fires in the railway's vicinity. A 400 litre tank has also been
obtained and will be mounted on a trolley.
Puffing Billy - Emerald Tourist Railway
Board
The PBPS has been
upgrading its constitution to incorporate changes in
company and other law since its last revision.
The PBPS is a company limited by guarantee and
is subject to Commonwealth Law unlike
most Heritage Railways which are incorporated
under the Incorporations Act.
The railway is
in the midst of a successful "Day out with
Thomas" season. These are held at Emerald Station.
The railway is planning its strategy to attract
more young people to volunteer with the
railway as the future of the railway depends on the
next generation coming along and learning the
necessary skills. To this end they are holding
a special weekend in May to try to attract young people.
As part of the railway's fire precautions the
railway made a decision not to run steam
engines beyond Lakeside and replace them with
diesel services when it was determined that the
surrounding countryside was extremely dry. Steam services have
now restarted to Gembrook. To add to the
fire precautions the railway has re-instated
its Water Tanker 149NQR into service and will
locate it strategically on the railway. The unit has
been equipped with spray nozzle's which will it allow
it to attack sleeper fires and conversely be used to
spray the track. The unit also has fittings which
will allow CFA tankers to take water.
The new Diesel DH 05 is almost complete and
has moved under its own power for the first
time. Once it is available for traffic it will
allow the line to run a better service
on days of total fire bans. A lot of work has
been carried out to clear the lineside of
saplings and shrubbery which could burn
in a bush fire. Quite a bit of work has been
concentrated in the area adjoining the Wright
Forest.
As part of the change over
of radio and television communications in Australia,
new digital radio systems are to be purchased
and installed on the railway.
The
railway is upgrading its archives and is
seeking any items of historical significance to include
in them. After all 55 years have now elapsed
since the PBPS was formed and most of
our founders have passed away so it is important
to obtain documents and other artefacts
of an era that is gone. Although 3NA is
only a skeleton in our storage sheds this month (April)
has seen the centenary plus 10 (110) of the first of the
locally built NA class steam engines.
Museum
Although not part of the
Museum exhibits now but a long term resident, the Climax
engine 1694 has successfully passed its boiler test.
This is the successful completion of the major
part of the restoration of this engine. Work will
now concentrate on the motion. The boiler is
now stored dry and will wait until such time
as the remainder of the works are completed before
it is placed in the chassis. It must
be borne in mind that the whole railway is a living
museum.

Climax Engine at Belgrave Workshops after
the Steam Test
Present exhibits in the Museum
such as the steamroller are receiving attention and the
roller has been stripped to its component parts
and the boiler is in the works at Belgrave to
receive repairs. The Foden traction engine is
at Emerald as part of the Thomas days.
Steamrail
This year Steamrail has decided to target
the suburban trip market in 2010 and is running an
additional number of trips to suburban
destinations. Also on the list are weekend country
trips and four are being planned this year. It
is expected to visit Quambatook, Sea Lake,
Wycheproof and finally Swan Hill and Echuca on the
list.
The first tour of 2010 was to Bairnsdale using
S301 and Pacific National A78 and the introduction of a
package lunch was a good success.
One of the main things to be finalised is the
matter and use of turntables in the country.
An open weekend at the depot in Newport was held in March
and was well attended with numerous demonstration rail
movements during the weekend. Up to six steam engines were
in steam over the weekend.

Tait Motor at Newport Workshops
Open Day
Steamrail has presented its new SMS to the
PTSV for review. This is for the operation of
rolling stock immediately outside its depots at
Newport and Ballarat East in areas not under
Steamrail's control.
Locomotives
T356 has had its sticking brake cylinder
stripped and cleaned out and it is
programmed to go to EDI Newport to have a lift
done. T364 has been languishing and it
is expected to complete the air conditioning fit
out by air conditioning contractors. S301 is to
have its noise level in the cab improved. It was found
that the old material had degenerated
and the new work has shown a marked
improvement in noise. S313 is also to have
its cab insulation replaced.
All the steam engines have been stripped for boiler
inspection and all passed the annual inspection. While
each engine was stripped the opportunity
was taken to do some
minor remedial work. K190 has been placed in dry
storage as a strategic spare engine should one
of the other engines fail during the year. R700
which is at Ballarat is being got ready
for its eventual transport to Newport. This
engine was a former West Coast Railway
unit. A2986 has seen the completion of work on the
driving wheels. The slide bars have been built
up and sent away for machining. The drag box
has been almost completed. One
difficulty with locomotive running lights is
the vanishing of incandescent globes (32V and 20
watts) and a small stock was obtained from a
supplier in South Australia.
Carriages
2BS which ran on the Bairnsdale trip was
found to have a fault with its air-conditioning
unit.. The fault was traced to a lack of
refrigerant. Moorabool in a trip last year
developed a fault in the HEP system and it was necessary
to replace the burnt out components to get
the car fully operational.
The Victorian Goldfields Railway
Following on from the fire at Maldon Station,
reported in Issue no 44 of the News, the entire station
roof has been removed and the chimneys stabilised. The
fire has meant that the power supply in the area
has had to be reworked to allow the reconnection of
the workshop and to the temporary station building (
loaned from Puffing Billy). Work has started on the
new toilet block at Maldon .
The proposed carriage shed at
Maldon is not to proceed as further investigation
has shown that as more and more passengers are
joining the train at Castlemaine, it
is better to build the facility at Castlemaine.
Approval in principle has been received from
Regional Development Victoria to transfer the funds
from Maldon to Castlemaine. Early discussions are
being held with the Shire of Mt Alexander to
build the shed at Castlemaine.
A big clean up of Maldon yard has
occurred and a transfer train of 19 wagons operated in
early February taking the stock to Castlemaine. The train
was hauled by Y 133 and the load was 230 tons. As part of
the clean up at Maldon, 3 vehicles which were
considered to be beyond repair were scrapped
WW 143 was an exception and has gone to a
member.
The February shutdown allowed the
railway to undertake further maintenance
on the bridge at Muckleford and seven piles were
replaced and one main beam together with other
work. Work has started in preparing the level
crossing on the Bendigo road with flashing lights
and the lights themselves are being refurbished at
the Seymour Rail Heritage Centre. Ballasting of the
track in this area has also taken place.
The railway's E carriages are
being prepared for transfer to Seymour for
long term storage and restoration by that
group. In order to make Muckleford yard area better
for special events It is proposed to further
develop No 3 road.
All steam engines K160, J 515 and
J 541 are in service and work is continuing on J
549. With the presence of a crane at
Maldon in February as part of the Maldon clean up, it was
used to lift K 157's tender tank off its frame
to assess the condition of the frame and the tank.
Tramway Museum Society -
Melbourne Tramway Museum
The group has issued two full
coloured news letters since the annual meeting and is
imploring people to volunteer at Bylands. They
have adopted a new trading name "Melbourne Tramway
Museum" The visitor reception is being moved
to the main display hall and the previous building
is being renovated.
The Museum hosted a day for
volunteers from the Mitchell Shire Tourist Information Centres.
One of the historic cable trams has temporarily been
taken to hospital. As part of the 150th anniversary of
Kilmore Hospital the cable tram was transported to
the hospital to be part of the celebrations.
The Museum reports that thefts at
the site are continuing and tool and tram parts have
been stolen from a shed recently. Also a large quantity of
rails and pointwork which was stored at McKerchers road
prior to being removed by the Museum to Bylands was
also stolen.
The Museum has some archive material at
Malvern Tramway Depot and this is being catalogued
to distinguish this material from those
owned by the AT&MOEA and Mr Norm Maddocks.
The Museum is working on achieving
accreditation but this will be a long and hard task as the
Museum is now treated as a new body and has to
prove to the PTSV and the Department of Transport
that it is a suitable body to run a
railway.
Yarra Valley Railway
The railways has at last achieved
one of its goals in being able to run full sized
railway vehicles on its line carrying paying
passengers. RM22 has been accredited to carry
passengers once again and is now in service. The
railcar now runs from Healesville to the block post
beyond the tunnel. Additional drivers are being
trained. The days that the railcar is not running,
the service is supplied by the
normal trolley trips.
All photograph by John Frost
unless otherwise attributed
Updated April 2010