Recently a public lecture was held at the
depot on the History of Melbourne's Cable Tramways.
The talk was given by Mr Robert
Green and started with an illustration of newly
discovered cable tram tracks still in the road
at North Melbourne. The community had
forgotten their existence and recent road works had
rediscovered them. It was appropriate that the
tracks found were immediately in front of the
former Cable tram Depot and where the present
electric trams pass.
It is hoped that this talk will
become the start of more talks
on tramway history.
The VicTrack promotional calendar for 2009 focuses on the
Melbourne Tram Museum @ Hawthorn Depot and heritage tram NMETL
No 13. The calendar is a large poster suitable for wall mounting
or framing.
Principal photography for the calendar was taken on Wednesday
19 November 2008.
Hawthorn Depot was built in 1916 for the Hawthorn Tramways
Trust, and designed by noted Melbourne architect Leonard
Flannagan. It became the location for the Melbourne Tram Museum
in 2003, after a major redevelopment project, and is now home to
twenty historic trams.
Previous issues of the calendar have featured other key
Victorian heritage rail assets under the management of VicTrack.
The 2008 calendar focused on the historic Maryborough railway
station, once described by American author Mark Twain as a
railway station with town attached.
A limited number of copies of the calendar will be available
from the Melbourne Tram Museum on our next
open
day on 10 January 2009, free to visitors on a first-come,
first-served basis.
The Association has decided not to restore tram SW5 843
but to fully restore SW5 849 in place of
the former tram. After corrosion was found in the
panels and frame of 843 an assessment was made of both
vehicles and it was found that 849 was in better
condition than 843. The original proposal was
to scrap 849 for parts but this has been
reversed and as 849 received frame repairs
and new panels in the 1980's after
receiving the agreement of VicTrack this is
now the tram to be restored. 849 is now
in the car barn and 843 has been placed
outside to be dismantled. 849 has been cleaned and
serviced prior to running and damaged parts removed for
restoration. Other parts have been replaced.
Insulation tests have been conducted on the
traction motors and the axle boxes bearings checked with
No 4 axle box brass requiring renewal. A risk
assessment , checklist of fit for service and a
change of validation were collated and submitted to
he Committee and the PTSV. The car ran for the
first time under power at Haddon on the 22
November 2008.
Remedial repairs were needed to correct the
footing to Container No. 2 which started to subside slightly
after some heavy rain softened the soil under it. Once the
ground dried out sufficiently, the container was jacked back
level and footings were dug under the container and concreted
in.
The opportunity was taken
while having the concreter and concrete truck on site to also
install a new pole 7 beside
the Tower Wagon Shed to replace the existing pole 7 which will be removed to
open up clearances between the Tower Wagon Shed and the Mainline.
Some ongoing overhead maintenance was also carried out during
October, with KymSmith carrying out some adjustments to the span between poles 6
and 6i, and some
initial re-tensioning of the contact wire at the Upper Terminus
The tower wagon shed has
been extended and shelving installed with the spare
overhead material sorted and catalogued. In the main storeroom the
sorting and stacking of parts is almost completed and work is
concentrating on the provision of a test room where it
is proposed to relocate all the air equipment.

W4 670 and L 103 in the sunshine at Haddon
Photo Bob Wilson
Puffing Billy - Emerald Tourist Railway
Board
The annual run for the
children with Thomas was held in November. The
railway has extensive archives and is in the
process of placing movie film onto DVD and then
transferring this onto what ever medium
is the norm for the current generation in the
future.
Carriage 8NBH has been
restored to "as built" condition with canvas blinds,
leather straps to hold them in place, full length
running boards and hard uncomfortable seating. No
modern upholstered seats for this carriage. It was built
in 1919 and in its 90 years was modified by
both the railways and Puffing Billy to make
the carriage more comfortable. The railway needed to
keep one vehicle as a reminder of the way
passengers were accommodated early last century.
The railway has prepared a new Business Plan in an
endeavour to source funding required to keep the
railway up to the mark. As with all
heritage railways the finding of capital
is always a problem.
The Museum group
has restored the George and George boiler to
service and the Malcolm Moore exhibit has also been
restored.
Work on the Climax engine
is steadily proceeding and the boiler
will be ready shortly for its hydraulic testing
prior to its first steam test. G 42 is to undergo
a D examination and will be out of service
for several months.
The railway
has completed a platform and buffer stop
at Sorrento and has repaired the Newport Workshops
Garden Platform. This platform at Newport was regularly
used by passenger trains in the past
providing a service for the thousand or so
workers at the railway workshops. It is
now in the Steamrail precinct.
Seven - O - Seven Operations
The railway's website has been revised and is
most attractive.
Discussions are
taking place to prepare 2009's itinerary and this
will be placed in our events page when
they are advised. The Association is repainting
their carriages. A project is underway to re-paint the
carriages red with a grey roof. The shade of red is that used by
Victorian Railways in the 1940s on the "AS" and "BS" carriages
that were not used on the Spirit of Progress.
R 707
In 2008 engine R707 m has seen the
overhaul of its Westinghouse brake components, and the
replacement of the front bogie rocker pins.
T 413
T413 was built in 1955 for use by the Portland Cement Company
at Fyansford. It was numbered D1 and differed from the other 1st
series locomotives in being equipped with dynamic braking and 3'6" (1,067mm) gauge bogies.
It
was purchased by Victorian Railways in 1967, re-gauged to 5' 3"
(1,600 mm) and re-numbered to T413. The locomotive was based in
Wodonga and used mainly on the Cudgewa line where the dynamic
braking was helpful on the low speed line with continuous
gradients of 1 in 30 for 1 in 40.
T413 was acquired by 707 Operations in 2003. It has been
upgraded to maintain its mainline certification and is
periodically used by El Zorro for rail infrastructure work
(The above material is a precis
from the 707 web site)
Steamrail
Work is continuing by the contractors to
VicTrack to scrap unrepairable rolling stock. 32D a
swing door driving trailer, 64BW a country carriage, 31ZD
a van and GY 4346 and GY 16165 have all been cut up. The
area which is near the old tarp
shop is to be redeveloped for electric train
stabling.
All operational steam engines have been
stripped for their annual boiler inspections. Diesel T364 is
receiving general body preparation for repainting in VR
blue. Additional sound proofing is being
added to the cab and air-conditioning is being
fitted for the comfort of the crew. T395 also has
had an air conditioner fitted.
ELECRAIL DIVISION
The focus of the Elecrail crew over the past few months has been
obtaining parts (including good timber, screws, and electrical
parts) from vehicles to be scrapped as part of the shift from
the Tarp Shop area to West Block.
Time has also been spent reorganising spare equipment that was
brought across. Whilst this has proved a major distraction from
ongoing restoration work it should prove to be time well spent.
Many of the spare parts retrieved from 32D can be utilised on
24D should it be restored in the future. There has also been a
follow up workshop to review and refine the first cut of the
Elecrail Risk Register. As a result of this workshop a second
draft of this document has been prepared. Input shall be sought
on this draft from a number of parties before it is presented to
the Steamrail Safety Committee in early January. After several
months of major project based distractions we are pleased to
report that things have finally settled down again and
restoration work has resumed.
To recap on 2008, the biggest achievements for Elecrail are:
- Completing the finishing touches on double ender 470M
- Securing funding which enabled safety film to be installed on
the windows of the electric cars.
- Developing the Elecrail component of the risk register (which
is now in its final stages of review/refinement) - Relocating
equipment from the Tarp Shop area to West Block (including the
salvage of spare parts from vehicles to be scrapped).
- Making good progress with the restoration of Tait car 341 T.
- Advancing the restoration of swing door car 12BT.
After a number of years of feeling as though the group has been
treading water (through being unable to operate) perhaps the
biggest highlight for 2008 is the feeling that Government are
supportive of Heritage electric operations resuming under
Steamrail accreditation and that they are prepared to help us
through this process. This has provided a major boost to our
volunteers and we hope there shall continue to be good progress
during 2009 as we celebrate 90 years of electric train
operations in Melbourne.
The Victorian Goldfields Railway
The railway reports that the area
in which they run is extremely dry and fire patrol
have started early. The patrols are conducted using
a hi-rail vehicle. A proposal to build new
toilets at Maldon is being considered and is to
be re-instated on the site of the old toilets
demolished in 1950. Toilets have long been the
bane of all heritage groups.
Work has been carried out to
the slate roof of the Maldon Station and a long term
solution is being examined.
Following on from last
year, the line is closing during
February 2009 to allow essential maintenance
to be carried out. The railway has revised its
timetable to allow visitors starting at
Castlemaine to have a shorter time in Maldon with
the option of staying longer and
returning on a later train. In addition a bus
service has started on weekends as a trial.
2009 is the 125th
anniversary of the railway and this will be celebrated
in June.
Tramway Museum Society
Owing to the few volunteers that are
available to regularly open the museum,
commencing on the 1 January 2009 it has been decided
to only open the museum on the
1st and 3rd Sundays in the month from
11.00am to 4.30pm.
Mitchell Shire Open Day
Earlier this year, members of the local Kilmore Historical
Society paid a special afternoon visit to the Bylands museum.
During the course of that visit, mention was made that over the
years, with the change and increase in the population in Kilmore
and the surrounding area, many locals were not aware of the
museum or what it had to offer. Over ten years ago, the Society
held a publicised open day for residents of the local Shire,
however the response was not as expected.
However, in light of recent events and publicity in the local
press, regarding the Society's operational difficulties and
other activities, and the problems with the rail reserve to
Kilmore, it was decided that the time is right to once
again attempt to gain support from within the local community.
The Board has agreed to hold an open day at Bylands for
residents of Mitchell Shire. The day selected is Saturday 17th
January 2009, commencing from 1.30pm. Admittance will be by gold
coin donation, and as well as tram rides, there will be a free
sausage sizzle.
:
Museum Works
One long-standing task was to improve the
internal appearance of the visitor's section of the kiosk. First
impressions count, and in recent years, the interior of the
kiosk has become "very tired" indeed. Following repainting
and with the relocation of some furniture the
area has been improved.
Other around-the-site changes include filling potholes in the
entrance roadway (using old spoil and ballast from the main-line
rehabilitation), and the burning off of more of the former
Cyprus trees in the eastern paddock with sheep keeping the grass
under control.
A major effort has been made to get the pit
shed available for use. The Bendigo Tramways have been
contracted to undertake several tasks, including welding up all
the remaining joints in and on the pit shed track, including
installing the bonding. This was completed over several days
during late September and several joints in the
depot fan welded as well. They will return again soon to
install additional bonding along the main-line.
At the start of October we were advised that
we were required to remove our remaining items stored at the
former North Fitzroy depot which had been left over from our
restoration projects several years ago. This included two
large and heavy wooden workbenches, a tram compressor, side
doors of 19W, a large tool box and other incidentals. These were
transported to Bylands.
Tram maintenance continues with a number of
trams receiving their yearly services. An air leak in a union on
tram 612 proved so successful, that it caused another one
elsewhere. This is now under repair. One of the controllers on
644 is still causing concern. Adelaide H 373 has developed an
electrical problem, and this is now being investigated by the
Bendigo Tramways. We have experienced the theft of several items
out of this car of late, and consideration is now being given to
placing locks on all doors to restrict entry.
Yarra Valley Railway
Return of Walker RM 22 to
Service
On the 15th November 2008 RM 22
returned to service being officially launched by Ben
Hardman MLA and Member for Seymour. The
occasion was the opening of the Watts
River Bridge and the handing over
of the ATHRA award to the railway for the
bridge's restoration. The railmotor is on loan
from the ARHS Museum at Newport and took two
years at Healesville to restore the motor to
trafficable condition. The rail Motor has been
fully restored into VR blue and gold. The vehicle
is the only 153hp unit presently in service
until the Daylesford Spa Country Railway
returns its motor to service.
Other Works
The 38 Mile bridge at Watts Point Farm has
been restored and can again carry trains over
it. This has been one of the major
stumbling points on the railway. Work has been
going on and off since 1995 and is
finally finished.

RM22 at Healesville Station
Photo John Frost
Updated December 2008