Melbourne Tramcar
Preservation Association
The Association
has only a small number of carefully chosen
tram cars in its collection, and with the
smaller number of trams to maintain than other
Tramway Museums, much of the
present work is concentrated on the tram fleet.
The group
reports;
Tram maintenance
W3 663 Is
at
Bendigo all of the old plywood roof sheets have now
been removed and the scraping and varnishing of the roof ribs
completed. The replacement black wood ply sheets have been cut
to size and have been French polished prior to fitting.
Extra funding has been raised through the sale of surplus
equipment and donations from members to allow additional
restoration work to be undertaken, including scraping and
varnishing all of the bulkheads and upper areas in the driver's
cabs while the roof was removed. This work has been completed
and work has now commenced on re-roofing the car with one side
nearly complete. Lifeguards and the brackets associated
with them have been kept at Haddon and
are being restored there.
The drop centre
quarter panels are now being attended to with replacement safety
glass being installed. All the drop centre floor slats are to be
replaced due to wear. We have been able to supply Bendigo with a
full
set of new slats from our stock thus saving additional expense.
All the holes drilled in the side panels for advertising have
been welded closed and a number of minor rust areas in the drop
centre attended to.
Research into the various colour schemes used on both inside and
outside of the car when initially built is now being undertaken
to ensure accuracy of restoration. The finished result should be
most impressive and will complement the other restored cars in
our fleet.
The first sheet of new plywood installed onW3 663. The newly
varnished bulkhead is also visible. The car is being
restored to original condition.
SW5 849 The
fibre glass side marker light housings have been fitted to the
replacement No. 2 end apron. A set of replacement timber drop
centre seats have been removed from store and are to be
refurbished for this tram.
Workshop activities
A replacement wheel set has been fitted to
the spare set of No. 15 trucks to replace a wheel set that had worn tyres and flanges.
The replacement wheel and axle set came
from a recently dismantled truck obtained
with the other two trucks for this purpose.
Work is now concentrating on replacing
various worn or damaged brake
components and also on replacing various worn
or damaged brake components.
A number of
spare compressor/line breaker switches have been overhauled.
These have now been completed and will undergo inspection and
certification as per our procedures before entering the store
system and eventual use as change out units for our fleet.
Trackwork and
Buildings
Work has slowly progressed on the north-western
curve with the check rail being welded at the joints. A spare
guard rail from a set of points was cut in half to provide a
lead in to the check; the other half being kept for the other
end of the curve. At the Northwest curve
all the rail joints have been welded and ground
back. The inside rail and the checkrail have had all
the holes drilled in the web and they have been bolted
together. The sleepers have been drilled for
the inner rail and check rail and all that
needs to be done is to drill the web of the
outer rail for the tie rods and the sleepers for spiking
the outer rail. Of course they then have to be
spiked. Once this is done, work will start on
commencing the rebuilding of the south western curve
before overhead works are completed to allow
operation to commence on this track.
No 3 Road. A start
was also made in bolting up the first few bolts and tie rods.
Work is now well advanced in preparation to extend No. 3 road of
the Car barn with all materials on hand. The timber framed wall
for the rear extension area has been fabricated and truss
brackets have been fabricated. The rear wall has been removed
and the new extension framework erected.
Spare parts trams and storage
The dismantling of SW6 931 is now complete and the remains
will shortly be disposed of. Whilst the crane is on site to load
931 it is proposed to lift SW6 919 which is situated near by and
place it on stands to allow easier access to the under gear
equipment. Work will then commence on the removal of parts from
this tram. All of the spare traction motors have been removed
from the Truck Shop and loaded into the motor/compressor storage
container. Resulting from the demolition of W
class trams two sets of trucks have been
donated to the Ballarat Tramway Museum
and these have been transported to their
storage area at Bungaree.
A number of GE 247 motors are still to be removed
from condemned No. 15 trucks before this exercise is completed.
In the meantime, heavy duty pallet racks have been acquired and
set up in this container to store our spare air compressors. The
spare DH 16 compressors have now been placed on pallets and
loaded onto these racks. Additional shelving has been installed
in the Overhead Store to better accommodate the spare overhead
fittings and the parts rearranged accordingly.
With the removal of the traction motors, alterations to the
Truck Shop have now commenced. The rear wall of the Substation
has been strengthened and lined in preparation for shelving.
This storage area will house the collection of brake components
and bushes which currently remain unsorted in the B Van.
Working with Children
The organisation is looking at the need for
children checks in the future. A decision will be
made shortly.
Puffing Billy - Emerald Tourist Railway
Board
The railway mourned the death of Lon Wymond on
29 October 2010 who was President of the PBPS from
1961 to 1989. He was Chairman of the ETRB on its foundation from
1977 to 1984 and remained as a Board member to 1998. Lon
received an OAM in in 1991 and was elected an Honorary
Life Member of the PBPS in 1990. He will be sorely missed.
The railway also noted the death of Keith Atkinson who
for many years has printed the Edmonson
tickets for Puffing Billy. These days the Edmondson's
at Belgrave are only used as souvenir
ticket but are still in use at lesser stations.
Open Day
The Open Day in October 2010 was most
successful and it was a day where all volunteers
were asked to come onto the railway even
though most tasks were doubled and tripled up. It allowed
the volunteers to meet each other, often at
different locations to which they normally
work and with the special events at Belgrave,
Menzies Creek and Emerald and with the running
of a mixed goods train to Gembrook both
volunteers and passengers had a great day. In
2011 the railway will be running a "Gala Weekend"
building on the Open Day.
Funding
With the change in the State Government the
railway has missed out on the announced grant $10.3M
to do major works on the railway. For
over 110 years the rolling stock has had to stand in
the open and this has added to the
cost of restoration and leads to the deterioration of
roofs and paint work of the carriage fleet. Alas the line
will still have to wait.
Historic Carriages
The railway has purchased and transported to
Emerald two VR narrow gauge carriage bodies. Both bodies
are NB bodies. One carriage is an end platform
carriage and the other a swing door one. One
is believed to be 6NB. It is hope to
ultimately restore both carriages.
Locomotive News
In 1911 the VR built engine No 11NA which
was scrapped in 1953.
Climax Engine 1694 Work is slowly
proceeding on the Climax with the side frames
being repaired a pattern for the crank shaft bearing brasses
made and modifications to the brake cylinders under way.
The brakes are being converted from steam to air. The
crank shaft housing has been line bored and
the footplate brackets are being shot blasted and painted.
the countershaft preliminary machinery is 80%
complete with the engine tie bars being
installed. The committee ran the successful
mixed goods train to Gembrook for
the Open Day.
G42 Has had its D
examination completed. 7A is now undergoing
its D exam. 12A's rebuild is slowly proceeding
with two crossheads machined and the internal steam
pipes machined.

Puffing Billy Santa Train at Menzies Creek
2009
Steamrail
The railway had a successful season in 2010.
With the reduction of the extent of the rail
network, trips to far distant places are
not feasible and many of the steam trips
are topped and tailed by two engines as many lines
that are left, have no turntables
or passing loops. Consequently much of Steamrail's
steam trips are often within the suburban
area. While some longer trips are still
undertaken these have to be planned most carefully.
Also the "steam ban" comes into play during
the summer as fire restrictions preclude the
use of steam and it is only
possible to run heritage diesel trips. Looking at
he programme proposed for this year (2011)
only two trips go beyond the
larger rural cities and only seven trips
to those rural cities.
Nevertheless the suburban trips have increased in
popularity and will play a large part in the trips
planned for 2011.
D3 639 was loaned to 707 Operations to
run a trip for them as this engine
R707 needs major boiler work. All steam
engines are currently stripped waiting on boiler inspections
over the summer period. Engine R711 has been steamed
and it is hoped that mainline testing
can take place in 2011. A2 986 is having silver anti
corrosion paint applied to the whole
boiler in preparation for the fitting of sheet metal
around the boiler.
Carriage BS 207 is being sanded down preparatory to
its repainting. 8 AS is in the workshop
and a large rust hole was found which is to be cut
out and a new piece welded in. To do this the seats
, seat backs, floor heaters, insulation and wiring
needs to be removed and it may also
entail the removal of a window.
Tramway Museum Society of Victoria
The group
has held its annual General meeting and elected Mal
Rowe as Chairman. They have registered the trading name
of Melbourne Tramway Museum which causes confusion with
the "Melbourne Tram Museum@ Hawthorn Depot" registered by
Victrack for their museum at Hawthorn and the Melbourne Tramcar
Preservation Association at Haddon. The publication
"Running Journal " carries an article about a tram
body rescued by the Bayside City Council and
the Birney tram car being built in Christchurch, New
Zealand.
The Society has started a new e-newsletter for
T.M.S.V members entitled "from the Chairman's desk" to keep
members in touch. It
mentioned that the T.M.S.V is assisting in the
restoration of the VR Pengelly toastrack tram by
the Friends of Black Rock House. It also
mentioned that a grant has been received by
the Society for improving facilities at Bylands for
Volunteers.
The Victorian
Goldfields Railway
The new toilets and shop
have been opened by the local Member of
Parliament. With all the recent rain in the district
the local streams were flowing, and it was
instructive to see why the VR engineers
built them so high to cope with fast flowing
rivers and creeks. At Muckleford the creek was
two metres in depth rather than the normal
trickle.
Locomotive T333 is now working on the
main lines for El Zorro and is producing welcome
income for the group.

Train at Maldon Station
Yarra Valley Railway
The railway advises:
Bushfire Recovery Grant
The YVTR has been successful with a funding
submission to the Bushfire Recovery Community Infrastructure
Program through Regional Development Victoria, the funding grant
is sponsored by the Bendigo Bank. The funding will be utilised
for the reconstruction of the timber trestle bridges within the
rail corridor which were destroyed in the Black Saturday
Bushfires. Engineering assessments and the redesign process for
these works has commenced.
Work for the Dole
The YVTR has recently achieved the status as
a Host for a pilot Work for the Dole scheme. This program is
brokered by Mission Australia and funded by the Department of
Education Employment and Work Place Relations (DEEWR). This
activity will focus on restoration works along the rail
corridor, buildings and infrastructure, assisting the YVTR in
achieving their restoration goals.
Reconstruction Plans
The receipt of the Bushfire Recovery Grant
combined with the donation of materials from the Department of
Transport and Metro, has enabled the YVTR to accelerate its
reconstruction plans. The immediate goal of the YVTR is to
commence passenger trolley services from Yarra Glen Station to
Train Trak Winery, approximately 3km, with further plans to then
extend the trolley service to Tarrawarra, approximately 4.5km
from Yarra Glen. The restoration of this section of mainline
will be completed to train standard in preparation of the full
restoration of the Healesville to Yarra Glen rail corridor. Line
side clearing is well progressed within the section between
Yarra Glen and Train Trak Winery. Track restoration works have
commenced at the Yarra Glen end of the rail corridor.

New track at Simpson's Lane
Photo Yarra Valley Tourist railway
Walhalla
Goldfields Railway
The centenary of the railway
resulted in an increase of visitors to the railway
and it reports that Easter 2010 was the most
successful yet and broke all records for
passengers carried. On Easter Eve the line
carried 944 passengers and on Easter Day 948
people. The railway carried 34,000 passengers in
financial year 2009/2010.
The centenary resulted in
excellent publicity with coverage in the
RACV magazine and there was both radio and TV
coverage of the Centenary. On the actual
centenary day the Minister for Tourism
and Major Events, the Hon. Tim Holding, travelled on
the train and unveiled a plaque to celebrate
the event.
While the actual opening of the
railway is well known, there is some discussion
as to the date of the last train on the railway which is
recorded as being the Friday 25 June 1954 and run by
7A instead of G42. It is recorded that this train cleared
the line of all rolling stock yet a
report has been made that a "final"
train ran on Tuesday 29 June 1954.
The advent of the Puffing Billy engine
7A in May was a huge success even though the
weather was extremely wet. As a result of the
Centenary, the financial results were
excellent and will allow the replacing of
piles in Bridge No 6 and the building of a verandah
at Walhalla Station. The years events have continued
to grow with "Murder on the Walhalla Express" being
booked out and it was enjoyed by all who took
part in it. The railway has become the venue for a number
of weddings and reception
The railway has taken part
in a Model Railway event at Sandown Racecourse
and the railway's stall helped the exposure of the
line to the public.
The railway has changed the
springing on the bogies on the passenger
carriages to give passengers a better ride. To
augment the motive power on the railway
a DH engine No 37 has been purchased and
has been delivered to Walhalla. It will
require re-gauging as it is 3'6" gauge.
All photograph by John Frost
unless otherwise attributed
Updated December 2010