Mornington Railway
The railway reports;
The railway has finished selective re-sleepering in the cutting
up (i.e. the railway 'up') from the Horse Crossing. Parts of the
railway that are in cuttings are the worst due to dampness, and
this one was no exception. Over the length of about 225 meters,
the gang replaced 69 sleepers, most of which were total scrap.
We have now moved to the section from the down Moorooduc points
to Wooralla Drive, and replaced 12 sleepers, with
15 to go to the gate. This section, also in a shallow cutting,
gave us some difficulties in the form of a large root that had
practically replaced one sleeper
K 163 Boiler Lifted
Off
The original plan to install a replacement boiler on K163 called
for the locomotive to be withdrawn from service after the last
running day in February 2010 so that the boiler swap and related
work could be performed. It was actually withdrawn several weeks
before that. The reason for this was the state of the ash
pan. The ash pan was known to be badly rusted and had the
potential for hot coals to fall through gaps in the weakened
steelwork and onto the track. The engineering team commenced work on removing
fittings, cladding, part of the cab and the fastenings which
secured the boiler to the locomotive's frame. The work was duly
completed by early April. Jacks were then placed under the
boiler and it was raised a small distance from its seating to
ensure that it would freely separate from the frame when the
cranes came to totally lift it out.
On Wednesday 31 March, with two cranes in attendance and watched
by a crowd of interested onlookers, K163's boiler was finally
lifted out of the locomotive frame and placed on the ground
nearby. A number of other heavy lifts took place on the same day
while the cranes were in the area. The restored K191 boiler was
brought out from under the covered area where the rebuilding
work had been carried out and it was placed in a position where
it could be easily lifted into K163 when required. K163's boiler
was then placed in the covered in work area where it will be
rebuilt as necessary for fitting into our second steam
locomotive
Following removal of K163's boiler, the engineering team focused
on removal/replacement of the springs and numerous other
suspension items. In addition, other components which were much
more accessible while the boiler was out of the frame were
inspected and remedial work carried out on them wherever
necessary. It was also a good opportunity to inspect and perform
any required maintenance on the main driving wheel brass and
white-metal bearings.
Within the next week or so, work will commence on re-assembling
the springs and suspension components with the aim of lifting
the replacement boiler into the frame in late June.
Carriages
Since June last year the Carriage Department has undertaken
extensive repair and repainting jobs to our fleet of vintage
carriages & guard vans.
Passenger carriages 24AW, 45BE & 57BE have all been repainted
and old signage has been replaced with new removable signs which
will make future repair and repainting easier. It was with a great
deal of satisfaction that we returned 57BE to service on Fathers
Day 2009 to mark its 100th birthday. Also 98G, our party
carriage, has undergone the same make over as the other
carriages. The guard vans, 5CV and 604ZD although having a
repaint, still require some additional repairs which will be
carried out over the winter months.
Currently 27BU is in the shed to undergo a face lift, after
which we will have 4 passenger carriages of a very high
standard. (I have heard from some of the conductors that the
passengers have remarked on how well turned out our carriages
are. This feedback makes all the hard work worthwhile). Guards
van 20Z is also going to have extensive repair and repainting.
Locomotives
T334 - In Service
This loco has been sharing the running day duties with T411 and
when not out on the line many hours have been spent bringing the
loco back up to a high standard with a lot of maintenance work
being performed. This includes ongoing maintenance, cab
improvements and a fair amount of work on the engine as well.
There's still a lot to do but the diesel team are progressing
well.
T411 - Under Cosmetic Restoration
At the time of reading this, T411 will have been removed from
regular running operation and will be undergoing its cosmetic
restoration. Up until now the loco has been performing well
sharing the running day duties with T334 and has been doing a
number of additional duties as well, this includes works trains,
shunting duties and driver experience specials. The decision was
made in 2009 that T411 was well due for rust repairs and body
attention so we are taking the time to carry out these repairs
as a part of the restoration. We intend for this to not take
longer than 2 months.
Melbourne Tramcar
Preservation Association
The tramway
reports:
Open Day
A successful open day
was held at the depot on the Sunday of the Ballarat
Heritage Festival in May.

L Class tram at Haddon
Other News
A
draft development plan for the Association has been submitted by
the General Manager, Anthony Smith to the committee for
discussion and comment. This plan contains various
recommendations on all outstanding projects and how we could
accommodate the proposed acquisition of a W5 Class tram. The
plan will be discussed at the next Committee of Management
meeting and the final proposal circulated to members for comment
and feedback.
On
Sunday 17 January as part of their "County Canter", members of
the Ballarat Vintage and Classic Car Club visited the tramway.
The number of cars on site exceeded 70 with all available
parking areas taken. We even had cars parked on the nature
strip along Sago Hill Road. It was quiet a sight to behold and
it is unfortunate that we were unable to record the event on
camera as only four members were in attendance to handle the
crowd which exceeded 80.
Filming took place at Haddon on Saturday
20 February 2010 for a Metro Trains Melbourne Staff DVD, one of
a regular series produced as a training tool. The purpose of the
DVD's is to encourage safe working practices by discussing with
drivers how they remain focussed and deal with the various
problems they are confronted with in their day to day working
environment. At the end of each of these productions they have a
feature section on drivers and what they do in their time off,
and for this disc the trams at Haddon were chosen for the
feature. The film crew spent a number of hours filming the
segment, and also provided the Association with copies of the
footage and some still images that they took.
W3 663
After carrying out a thorough assessment
of the roof structure with the Bendigo Tramways coachbuilders it
has been confirmed that because of its poor overall condition it
will be necessary to replace the entire roof boards. In order
to maintain originality, plywood sheeting will be used as the
replacement material, though an improved method of installation
will be used. The last group of W2's and all the W3 and W4 class
trams were built new with plywood roofs as an economy measure
during the early 1930s.
Work has commenced on stripping the roof
with the trolley pole equipment and bridges removed along with
the route boxes. The vent roof plywood section has also been
lifted. A quotation has also been sought from Bendigo for
additional work to be performed on this tram whilst it is there,
subject to available finance. Donations to assist this project
are welcome, and will assist in completing more refurbishment
work so that there is less to do when 663 returns to Haddon.
SW4 849
The replacement apron ex 809 has now
been fitted to the No. 2 end and a refurbished headlight
assembly fitted. The rewiring of the headlight and marker
lights has now been completed and the light units at the No. 1
end also attended to. The driver's bulkhead glass has been
removed and will be replaced with new material as the original
glass was etch primed to blackout half the viewing area. Work
will shortly commence on the replacement wooden drop centre
seats and the interior refurbishment of the car. Progress has
been a bit slower than had been hoped for due to other work
commitments around the site by Anthony and Jacqui Smith, the
regular workers on this project.
Storm Curtains
During the later half of 2009 we were
able to raise sufficient funds to commission the machining of
two sets of storm curtains for fitting to L 103 and W4 670.
Through the Bendigo Tramways we were able to obtain a very
competitive quote for this to be carried out by Thorpe's Canvas
Products at North Bendigo. The fitting of these new drop
centre storm curtains has completed the restoration work on L
103.
W4 670
In addition to the installation of the
new storm curtains, additional off side bell blocks were
manufactured during January and fitted to W4 670 along with two
polished and lacquered bell assemblies. All passenger carrying
trams in the collection now have these additional bells fitted
to allow for off-side running at Haddon.
Overhead
An additional steel pole has been
erected at the rear of the Car barn in the vicinity of the
north-western curve to allow tensioning spans to be connected to
the trolley wire anchors of the three Car barn roads. The main
function of these spans is to balance the load placed on the
anchors so that the tension of the contact wire and spans on the
Car barn fan can be maintained.
This pole will also be utilised in the
support of the redesigned network that is to be erected once the
relaying of the north-western curve is completed. During
March the old Pole 7 near the 5 Road points was removed and the
hole filled and levelled. This pole was replaced previously by a
new Pole 7 closer to the fence line to improve vehicle access.
Track work
Over one weekend in February the rail
and checkrail for the north-western curve was laid out and,
where needed, trimmed using the former SEC Yallourn rail saw;
its first use at Haddon. Bolt holes were drilled along the
length of the checkrail and the first length of the inner rail
using the newly acquired rail drill. Work to complete this curve
includes welding all rail joints, drilling the remaining holes
in the rails, installing the tie rods and spacer blocks, and
spiking the rails to the sleepers. Work can then commence on the
south-western curve to complete the connection to the mainline
straight track.
Puffing Billy - Emerald Tourist Railway
Board
Since the 8th June
this year Puffing Billy has been supported longer by the
Puffing Billy Preservation Society than the Victorian
Railways.
The Great Train Race
was held in May and was a great success, run in cool but dry
weather. The event requires a major effort by
hundreds of volunteers and members of the community
to organise each year as the run takes part on public
roads in the Dandenong's and this means that the
Municipal Council and bodies such as the police need
to be in attendance and agree to the event. As well
as providing the venue for the race, sponsors
have to be found and the race has become one
of the major events on the "runs" held in Victoria
each year.
The Puffing Billy
Preservation Society reports that John Thompson has
stood down as President and that Jeff Goodwin has replaced
him.
The new DH diesel is
now operational and is painted in the
traditional VR blue and gold. This gives the railway
the opportunity to run trains at normal speed
on days of total fire bans when steam can not be
used. These trips will still only run as far as
Lakeside on such days.
The railway
has reported a small number of slips and falls among its workers
and suggests that people be aware of
this when walking on platforms and yards.
Among notable events from the past the railway
mentioned that the Welshpool to Port
Welshpool 2'6" gauge horse tramway started 105 years ago.
June also saw the re-opening of the railway
between Belgrave and Menzies Creek which took place some
48 years ago.
Museum
The Museum reports that all the boilers on its
stationary and operating 2' engines have passed their
boiler tests. The Steam roller has been dismantled and the
crown stays have been removed and the motion
has had magnetic particle testing. It has been found that
the boiler has severe cracking in the pressed plate
work and side plates of the boiler
Visit of a locomotive to
Walhalla
Puffing Billy agreed to a request
from the Walhalla railway to allow an NA engine visit that
railway for the centenary of the opening of the
Walhalla line in 1910.
Climax Engine
Major Climax funding is now needed.
The Climax project has come to an important
stage. The boiler work has been finished and it is now being
stored ready for fitting to the frame. The next major work
involves the manufacture of axles, wheels and gear carriers. A
lot of this work must be done by outside companies and then the
finishing machining done in the Locomotive Workshops. In order
to keep the project going, the group has launched the Climax
Axles and Wheels Appeal to raise $95,000 for this work.
Metalock has been contracted to repair cracks
in the main engine frame castings that the cylinders are bolted
on to. They will also be repairing the transverse engine frame
beams. They use an ingenious method to fix cracks in cast iron
that would otherwise be very difficult or impossible to repair.
The cab and water tank are about to be removed and stored at
Gembrook. This will enable the floor to be removed. The frame
will then be inspected and repaired as needed.
Open Day
The railway is holding an open day
on 3 October 2010 and will show all aspects of the railway
to the public.
Steamrail
The
open day in in March coincided with the worst
weather to strike Melbourne for a long time
but some 1200 people braved the weather to
come and inspect the Newport Site. The
next open day will be in 2012.
Once again the
group took part in the Good Friday appeal for the
Children's Hospital and a set of carriages and D3 639 were
displayed at Spencer Street Station. Local
suburban rail trips have proved popular this year
and several are to be run later in the year.
Locomotives
The
railway has reported that all locomotives are
performing satisfactorily. R711 has been inspected by the
RTBU and found to be satisfactory and is now
in the process of being approved by V/Line. It
is proposed to move R700 from Ballarat
to Newport by rail. Y112 is being
recertified. A2 986 is proceeding in its
rebuild and it is examining the
possibility of employing some part time tradesmen to speed up
work. Lots of time consuming small projects
have been completed but the amount of work to be
done is huge and really is a complete
rebuilding of the engine. The money received
from the insurance of K183 is to be used to
speed up the restoration of the A2.
Carriages
Work on 61BW has been done and the carriage has been
repainted. The Electrail group is still
working away on restoring their carriages and
the bogies under 327M have been exchanged. The
air-conditioned carriages, Werribee and Moorabool, have
been giving trouble with the air-conditioning.
Werribee had a failure of the voltage regulator and as a
result the batteries boiled and ran dry causing considerable
damage. Moorabool has not been pumping the cooled air
through and the filter has been cleaned and the
thermostat adjusted.
South Gippsland Railway
The railway has taken delivery of the DERM
from Maldon and two wooden bodied carriages on loan
from Steamrail. The railway has seen a surge
in the number of passengers travelling and needs the
additional carriages to meet demand in summer.
The Victorian Goldfields Railway
Founding member, Vance Findlay, has stood
down from the Board of the railway after many years
of service. The railway reports that the new
shop and toilet block at Maldon is under way and
is well advanced. The new block is being painted
A new shed is being erected at Muckleford to
accommodate a blacksmith's forge.
The four E class carriages will be
transferred to Seymour for under cover storage and
restoration. K160 is to go to the EDI workshops at
Newport to have its wheels turned on the lathe. DERM RM 61
has been transported by road to Korumburra for that
railway to use while their own rail motor is
being overhauled. As part of the deal, DRC 43 which
is based at Seymour is to go to Maldon
for the C&MR use. Flat top T 333 has been at Seymour for a
number of years and has had sound proofing fitted in the cab, up
to date vigilance control fitted, and refurbished wheel sets.
Mainline tests are about to be trailed and it is hoped
that it can again be used to earn some
revenue on the mainline.
The railway reports that they had
a small financial loss in 2009/10 of $2,755. This was due to
the global downturn and it is expected that
the next financial year will be in the black.
No 3 road at Muckleford has now been completed
with ballast.
Walhalla Goldfields Railway
The railway celebrated the centenary
of the opening of the railway in 2010. The line was
officially opened by the then Premier of Victoria ,
Mr John Murray, on the 3rd May, 1910. In place of the
Premier in 2010 the Minister for Tourism and Major
Events was present at the centenary ceremony.

7A crossing the Thomson River
A number of events were held to
celebrate the centenary and the most notable one was the
arrival of 7A from the Puffing Billy railway to
run 6 public trips only. The trains were a great
success and the trips ran in what can be described
as "Narrow Gauge" weather, lots of drizzle and rain.
The sound of an NA engine's whistle re-echoing around the
hills from Thomson to Walhalla had to be
heard. The train was driven by Puffing Billy
personnel. 7A hauled the very last train on the Walhalla
line in 1954 when G42 failed.
It was necessary to inspect
the track and a few minor modifications were carried out
as the railway, while following the old alignment
when it was rebuilt,
is not exactly in the same place as the
original line and needed to be checked for
clearance.

7A renumbered as 9A at Walhalla. (9A hauled
the very first train into Walhalla in 1910)
Yarra Valley Railway
RM 22 is about to go into traffic
having completed its trials and being accepted by
the PTSV. The line has received a large number
of second hand wooden sleepers made redundant by
the concrete sleeper project in the metropolitan railways.
The railways' T class diesel T 341 is
operational and ran to Melbourne with
classmate T320 on test and to assess the engine.
The regular Saturday and Wednesday evening
track work days are still going flat out, with sleeper
replacement having reached Watts River, and around
the 38mile curve towards Bridge 28. The first load of ballast
was dropped in this section in mid February, with more to follow
as it becomes available. The track is now sitting several inches
above the road bed for the first time in many years, so
protecting the sleepers from rotting.
The Yarra Glen station area has received a
lot of attention over the past few of months. In the fires of
Black Saturday last year, the many large pine trees around the
station were either killed or so severely damaged that they had
become dangerous and required removal, a huge job which was
finally started in December and completed in mid February. Talks
in regards to the Yarra Glen bypass, in particular about the
Melba Highway crossing upgrade, are currently progressing with
government bodies.
The Nissan Patrol high rail has received a
much needed tone up, including conversion to broad gauge. The
paperwork is currently with PTSV and we look forward to seeing
the Patrol and Canter out on the rails soon. David Ingram, the
Lineside Co-ordinator has not been idle since our last report
either. In line with Management's do it once, do it right'
approach, the whole lineside between Watts River and Tunnel
Cutting has had the undergrowth cleared away, the edge of the
track scarified, ready for re-sleepering and ballasting and the
drainage re-instated.
In particular Devil's Bend has had decades of
tea tree growth removed, opening up views of the Yarra Valley
not seen for years. The importance of this work in relation to
the long term well being of the railway cannot be overstated.
One thing that all the civil engineers who have inspected our
line agree on is the necessity of upgrading and maintaining our
lineside drainage. The next area to see major work will be the
section between Lubra Bend and Steels Creek, when, as well as
drainage work, the huge job of removing blackberry, gorse bush
and other non-indigenous plants is to be tackled. We hope to
have this completed by the end of May.
The area around Tarrawarra has not been
forgotten, with the clean up and removal of dead bush fire
affected trees along the straight between Lubra Bend and
Tarrawarra ongoing when time and labour is available. Several
members have recently paid for the line side slashing of both
sides of the entire railway between Stables Crossing and Steels
Creek, a fantastic gesture that is much appreciated.
Carriage 1 BW is steadily being
rebuilt and has been turned to allow work to
continue on the corridor side. W 250 has had an ABC
exam and is in use on ballast trains.
All photograph by John Frost
unless otherwise attributed
Updated July 2010